HYDROELECTRIC GENERATING STATION Proj: 9126423-10
Muskoka Lakes Twp, Muskoka Dist ON WORKING DRAWINGS
Bala Falls Small Hydro Project, Hwy 169 and Hwy 38, Village of Bala, P0C
$25,000,000 est
Start: October, 2013 Complete: October, 2014
Note: Environmental Assessment has been completed by the consultant. Detailed designs are underway. General contractor will be secured privately. Construction is anticipated to begin fall 2013.
Owner: Swift River Energy Ltd. Website is: www.balafalls.ca.
Project:construction of a new generating station facility.
Development:Engineering
Category:Elect power, building; Elect power, engineering
Project manager Complete information is available to subscribers. Click HERE to find out how to subscribe.
Landscape architect Complete information is available to subscribers. Click HERE to find out how to subscribe.
Civil cons eng Complete information is available to subscribers. Click HERE to find out how to subscribe.
Consultant Complete information is available to subscribers. Click HERE to find out how to subscribe.
Owner's representative Complete information is available to subscribers. Click HERE to find out how to subscribe.
First report Fri Oct 08, 2010. Last report Mon Jan 21, 2013.
This report Fri May 10, 2013.