December 5, 2012
PARKIN ARCHITECTS LIMITED
The 17,000-square-foot addition to Georgetown’s hospital will result in a new emergency department and diagnostic imaging. The new one-storey addition will be clad in masonry and tied into the existing hospital.
Project coordination key on Georgetown hospital project
Like most hospital construction jobs, the 18-month, $9 million contract to build a 17,000-square-foot addition at Georgetown Hospital has its complications.
But even before starting that addition for a new emergency department and diagnostic imaging, general contractor Chart Construction Management Inc. has been busy.
“The site works phasing required numerous emergency vehicle and public access routing relocations in order to construct the new parking lot and emergency department ambulance entrance bay,” explains Jason Orzechowski, owner of Concord, Ont.-based Chart.
“We needed to complete it is so we could get into the ground with the addition before winter.”
The new one-storey structural steel addition will be clad in masonry and tied into the existing hospital. Once it is completed (the schedule calls for it to be operating next August), Chart will proceed with a 3,000 square foot renovation to the former emergency department space.
Renovations include asbestos abatement and interior gutting in preparation for ultrasound and radiology fit-outs, says Orzechowski, adding that infection prevention barriers will be “a high priority” because the work will be adjacent to fully occupied departments.
The barriers will consist of air tight framed walls sealed with six ml poly/drywall and a negative air pressure system.
Chart has plenty of experience with hospital projects, big and small. The contract at Georgetown ranks as one of Chart’s biggest, he says.
The approach to building health care additions like it today is more complex than in the “pre-SARS” (severe acute respiratory syndrome) years, he points out.
Construction methods — particularly infection prevention — swiftly changed after SARS hit Toronto in 2003.
“Now, how we build and how we get things done can be very tricky. Builders in healthcare need to be able to adapt to the advanced technology and the evolving demands of each healthcare project.”
“A lot of preplanning and coordination with the user groups is expected, and we have to engage in more education in infection prevention training such as that offered by the CSA as a mandatory requirement,” he says.
| MOST POPULAR STORIES |
- OPG $1 billion proposal to bury nuclear waste up for comment
- Hundreds of workers to be out of work as Caterpillar Inc. is set to close Toronto factory
- Ontario prompt payment bill to get second reading today
- Construction on pedestrian tunnel to Billy Bishop Airport continues to make progress
- Proposed Ambassador Bridge twinning draws Windsor mayor’s ire
- 20 Most Popular Stories
| TODAY’S TOP CONSTRUCTION PROJECTS |
These projects have been selected from 316 projects with a total value of $2,787,806,637 that Reed Construction Data Building Reports reported on Friday.
SENIORS CONDOMINIUM APARTMENT & OFFICE BLDG
$90,000,000 Richmond Hill ON Prebid
$82,000,000 White River Twp ON Tenders
CONDOMINIUM APARTMENT BUILDING
$40,650,000 Markham ON Prebid
| CURRENT STORIES |
- VIDEO: Competing in the trades
- Multi-employer approach needed in apprenticeships
- New Perspective
- ACEC’s input helps develop global engineering guidelines
- Clerk of works position gives peace of mind on projects
- World Trade Center developer’s plan for a 926-foot tower moving ahead
- Call for action after MOL says workers are responsible for their own safety
- Cold spring and weak construction hurt Deere’s 2013 predictions
- CanBIM reschedule June session
- More green roofs top Toronto buildings
- Witness recants testimony in Montreal corruption case
- Construction Site Arson
- Journal of Commerce Update for the week of May 20th, 2013
- Industry reacts to surprise B.C. Liberal majority
- Calgary Airport Tunnel
- Worker at centre of union sign up allegations speaks out
- Calgary program aims to get more people into the trades
- Midrise in the City
- Veterans battle barriers into the trades
- Government makes changes to online tendering
- SNC-Lavalin maintains that new bribery allegations have been resolved
- B.C. faces a tough battle for top talent
- Keyano College building state of the art training facility
- Essential skills can play a vital role in an apprentices' success
- Taking a closer look at the risks in green building for contractors
- Colleges conduct construction research in addition to teaching
- Skills Canada BC Competition
- Lower Mainland high school trades program is unique
- Construction Learning Forum aims to educate
- High schools looking for more industry participation
- Industrial construction supervisor program takes off
- Saskatchewan bill passed
- Edmonton garners support for regional cash for arena
- Feds pledge $5 million for Vimy memorial
| ALEX’S ECONOMICS BLOG |

Reed Construction Data Canada’s Chief Economist Alex Carrick discusses current developments in the North American economic environment with emphasis on the construction industry.
- An Overview of Prices and Sales in the Diverging U.S. and Canadian Housing Markets (April 25, 2013)
- Canada’s Precarious Dependence on the Commodity Price Super-Cycle (April 22, 2013)
- Twenty major upcoming residential and transportation terminal construction projects - April 2013 (April 15, 2013)
- More