LATEST NEWS
Trade Contracting
April 30, 2008
U.S. says millions of dollars worth of Iraq construction contracts never finished
WASHINGTON
Millions of dollars of lucrative Iraq reconstruction contracts were never finished because of excessive delays, poor performance or other factors, including failed projects that are being falsely described by the U.S. government as complete, federal investigators say.
The audit released Sunday by Stuart Bowen, the special inspector general for Iraq reconstruction, provides the latest snapshot of an uneven reconstruction effort that has cost U.S. taxpayers more than $100 billion. It also comes as several legislators have said they want the Iraqis to pick up more of the cost of reconstruction.
The special IG’s review of 47,321 reconstruction projects worth billions of dollars found that at least 855 contracts were terminated by U.S. officials before their completion, primarily because of unforeseen factors such as violence and excessive costs. About 112 of those agreements were ended specifically because of the contractors’ actual or anticipated poor performance.
In addition, the audit said many reconstruction projects were being described as complete or otherwise successful when they were not. In one case, the U.S. Agency for International Development contracted with Bechtel Corp. in 2004 to construct a $50 million children’s hospital in Basra, only to “essentially terminate” the project in 2006 because of months of long delays.
But rather than terminate the project, U.S. officials modified the contract to change the scope of the work. As a result, a U.S. database of Iraq reconstruction contracts shows the project as complete “when in fact the hospital was only 35 per cent complete when work was stopped,” said investigators in describing the practice of “descoping” as frequent.
“Descoping is an appropriate process but does mask problem projects to the extent they occur,” the audit states.
Responding, USAID in the report said it disagreed that its descoping of the hospital project was “effectively a contract termination,” but that it had changed the work because of escalating costs and security problems.
Mark Tokola, the director of the Iraq transition assistance office, also responded that the database the IG’s office reviewed of Iraq reconstruction contracts was incomplete.
Bowen’s office said its review was preliminary and that it planned follow-up reviews to investigate descoping more closely. Investigators said they were also looking into whether contractors whose projects were terminated by the U.S. government due to inadequate performance might have been awarded new contracts later despite their poor records.
Associated Press
| MOST POPULAR STORIES |
- Ministry of Transportation working with biggest road-building budget in its history
- Lethbridge, Alberta builder spends $2 million to turn water tank into restaurant
- Government should be more flexible with stimulus project deadline, outgoing ORBA president says
- Prime site moves from contamination to condo in Cambridge, Ontario
- Mine tower largest steel project ever undertaken by Gorf Contracting
- 20 Most Popular Stories
| TODAY’S TOP CONSTRUCTION PROJECTS |
These projects have been selected from 337 projects with a total value of $3,003,381,002 that Reed Construction Data Building Reports reported on yesterday.
$82,000,000 Metro Toronto Reg ON Tenders
CONDO BUILDING, HOTEL, THEATRE, RETAIL
$65,000,000 St Catharines ON Prebid
$40,000,000 Ottawa ON Prebid
| CURRENT STORIES |
- Peel Heritage Complex in downtown Brampton to undergo $11-million renovation
- New deal allows Canadian companies to bid on U.S. stimulus contracts
- ‘A good first step forward,’ Canadian construction industry says of agreement
- Government should be more flexible with stimulus project deadline, outgoing ORBA president says
- Ontario Road Builders’ Association honours volunteers who go the extra mile
- Prime site moves from contamination to condo in Cambridge, Ontario
- McGuinty: We can’t take our foot off ‘public dollar gas pedal’ too quickly
- Five still unaccounted for after Connecticut power plant explosion
- Non-residential permits up in December
- BMO executive sees U.S. housing rebound
- Brazilian dam contract to include $830-million environment levy
- Concrete from Giants Stadium demolition to be buried on site
- New deal allows Canadian construction firms to bid on U.S. stimulus projects
- Construction continues on Canadian Natural Resource office in St. Albert, Alberta
- Canadian Construction Association summit zeroes in on industry concerns
- Art Gallery of Alberta addition showcases steel
- 5,000-room modular lodging project taking shape near Fort McMurray, Alberta
- Five-year forecast looking up for British Columbia construction industry
- Saskatchewan gets new natural gas trades training centre
- B.C. permit numbers rise while Alberta’s fall
- Trades lack LEED understanding
- Nexen, OPTI Canada get approval for cogeneration power plant near Fort McMurray
- Aecon wins $22 million in contracts for steam generators
- SNC-Lavalin partners with Russian bank to form engineering company
| ALEX’S ECONOMICS BLOG |

Reed Construction Data Chief Economist Alex Carrick discusses current developments in the North American economic environment with emphasis on the construction industry.
- A review of some global economic and policy expectations for 2010 (February 3, 2010)
- Synopsis of RCD’s webinar on the economic and construction outlooks (January 28, 2010)
- Increasing signs of world and U.S. economies getting back on track (January 28, 2010)
- More






