March 28, 2008
Early May is the target for crews to be done the mining operation for the $76-million interceptor sewer construction in the town of Richmond Hill.
Innovation
York Region interceptor sewer project employs most current tunnel technology
A year after construction started, a $76-million interceptor sewer employing the most recent advances in tunnel technology is nearing completion in Richmond Hill.
“We should be finished the mining by early May and substantially finished by the end of June,” says Steve Skelhorn, project manager for McNally/Aecon, the joint-venture tunneling contractor.
Designed to relieve pressure on the close-to-capacity existing Yonge Street sewer without damaging the sensitive Oak Ridges Moraine, the 4.4-kilometre long 2,100-mm one-pass reinforced concrete segmented pipe is being installed by a Lovatt-manufactured earth pressure balance tunnel-boring machine.
The route is along 19th Avenue between Yonge Street and Leslie Street and a small portion along Leslie Street that was completed last July. A 1.6-kilometre sewer installed along that street by open-cut methods last year is also considered part of the project.
“We’re mining about 24 metres a day, which is the best production we’ve had and that’s been consistent for about 2 weeks,” says Skelhorn.
Tunneling at an approximate rate of 1.7 metres per hour, the tunnel machine is just west of Bayview Avenue heading west towards Yonge Street.
“The tricky part is well behind us,” says Skelhorn, noting the most complicated aspect of the project was actually at the start when two machines had to operate from a single shaft at Leslie Street and the 19th Sideroad. The second machine was for the excavation work along Leslie Street.
“We hope to commission the sewer sometime early this summer,” says Laura McDowell, manager of the York Durham Sewage System.
The commissioning will mark the end of a long planning and regulatory approval process for York Region that included considering nine alternative routes. Planning began several years ago, an environmental assessment was conducted in 2003 and a special dewatering permit was required from the Ministry of the Environment.
As the route is on the Oak Ridges Moraine there are several sections with artesian well-like conditions where the water table is above the level of the sewer.
“But we never had to withdraw any water,” says McDowell, citing the use of an earth pressure balance machine. The excavation technology provides continuous support to the tunnel face by balancing the earth pressure against the forward pressure of the machine.
What makes the technology so significant is the ability to work through almost all soil conditions, most notably water bearing soil, she explains.
“Conventional tunneling techniques require dry soil conditions and therefore dewatering is necessary in order to complete construction. We learned that lesson from another project.”
The earth pressure balance excavation wasn’t the only safeguard employed by the region and Earth Tech, its consulting engineering firm. Before work got under way, construction crews attended a special training session that dealt with issues such as sediment control and other measures for protecting the moraine. Workers were also required to place stickers on their hard hats indicating they had taken the course.
Construction was intensely monitored by regional and Earth Tech officials, says McDowell. “A lot of eyes were on this project.”
| MOST POPULAR STORIES |
- Korky Koroluk: Melting permafrost gives Canadian North that sinking feeling
- Two workers injured in separate accidents on Ontario’s Skyway Bridge
- Alberta continues to drive Canadian economy
- Volvo Construction Equipment cuts 500 jobs in Goderich
- Anthony Henday Drive ring road garners Canadian Design-Build Institute award
- 20 Most Popular Stories
| CURRENT STORIES |
- PCL Constructors team expands Air Canada Centre
- Debate sidesteps industry issues
- Ontario Realty Corporation registers general contractors, design firms online
- Stantec joins Infusion Health consortium on P3 hospital project
- Commercial banks stand to profit from Black Monday, economist says
- Economist warns U.S. economy on ‘slippery slope of recession’
- Daniels Corp. brings a taste of Chicago to Toronto condo project
- Facility and service managers must be full partners on P3 projects, expert says
- DCN election poll puts Stephen Harper’s Conservatives out in front
- Onni Group makes progress on Carlyle at Victoria Hill project
- Chinook Pipelines returns to court later this month in Pincher Creek case
| ALEX’S BLOG |

Reed Construction Data Chief Economist Alex Carrick discusses current developments in Canada's economic environment. He also shares light-hearted reflections on life and current events.
Economics Blog More 
- Huge Potential for Commercial Banks from Black Monday (October 3, 2008)
- Black Monday was Nasty for the U.S. and Canada (October 2, 2008)
- A 13-Step Action Plan to Fix the Financial Mess (September 30, 2008)
Lifestyle Blog More 
- Three Cities with a Lot in Common: Calgary, Edmonton and Venice (September 29, 2008)
- How to Get Ahead in this Life (September 25, 2008)
| PROJECT NEWS BRIEFS |
Updates on Canadian construction projects from Reed Construction Data’s research team. More 
- Viljoen Architects readies working drawings for Stonebridge by the Bay (Sep 15, 2008)
- REC Silicon plans $1.2-billion manufacturing plant in Quebec (Sep 15, 2008)
- Construction underway at Interfor’s Adams Lake sawmill (Sep 11, 2008)
- Alcan moves closer to construction of Kitimat aluminum smelter (Sep 11, 2008)
- Town of Oliver presses on with plans for wine village (Sep 11, 2008)
