February 29, 2008
SONCIN
Work in the Simcoe tunnel expansion was extensive but done under the radar to most. Above, girder installation takes extensive work power and precision. At middle, the tunnel footing is completed so work on the roadway can begin. Below, gantry erection takes place under the cover of night when road and train traffic is somewhat diminished.
Unique Challenge
Commuter traffic will gain new corridor as work done daily underfoot and undercover
$40 million tunnel expansion kept trains on track
TORONTO
Under ground and under the radar of passersby, a $40 million Simcoe Street tunnel extension has required military precision to build in one of North America’s busiest railway corridors.
“We could not close down any of the tracks overhead,” says Clyde Crocker, Soncin’s Simcoe Street Tunnel project manager. “The railway could have shut us down anytime if we slowed things down or created a problem.”
Soncin was contracted in May 2006 by Fairmont Developments to construct the extension of Simcoe Street, a four-lane underpass which has 13 active rail lines overhead. Construction had to occur without affecting GO Transit, VIA and CNR rail traffic through the Union Station corridor.
Even though the project unfolded in the heart of Toronto’s railway traffic and was surrounded each day by commuter traffic and nearby condominium construction, no one has really noticed the undertaking on Soncin’s plate, says Crocker.
Some construction sites across the Greater Toronto Area can proceed in isolation without much contact with the public. For Soncin, the public played a major role in its project planning.
“It was quite the undertaking,” says Crocker. “It was a complete team effort to make it all happen.”
The Union Station corridor has the highest train volume for a single terminus location in North America. Excavating 20,000 cubic metres of material and integrating the construction project’s schedule, without interrupting commuter and commercial rail traffic, posed unique logistical challenges.
Regular progress meetings with railway and city officials were held every two weeks.
“We needed to keep everyone in the loop and let them know what came next,” adds Crocker.
A key component in building the tunnel was the readily available supply of precast deck segments nearby. The project required 1.6 kilometres of girders so Soncin constructed a precast facility on site. A total of 153 girders were produced in three months. Fifty-one girders were post tensioned and 102 girders were normally reinforced.
The most challenging aspect of the project, besides working in a tight piece of real estate, dominated by rail traffic, was the schedule for construction itself, says Crocker.
Excavation and construction of the bridge’s abutment and piers occurred during regular weekday working hours. The new bridge’s deck provided the biggest and most meticulous planning challenge as it had to be built in sections and completed on pre-determined weekends between 7 p.m. Fridays and 5 a.m. Mondays.
The methodical phasing of this 20 to 30 feet worth of weekend work required everyone on site to be on the same page, says Crocker. With such a small window for construction on pre-determined weekends, precise installation was required. Soncin created an installation manual and supplied one to everyone who worked on the project.
“The manual detailed everything, right down to the smallest detail,” explains Dennes Soncin, Soncin vice-president.
“We wanted everything clear in everyone’s mind, from the foreman right down to the subs. Everyone understood what their function was.”
The project was divided into seven phases, each consisting of the removal of an existing temporary structural steel trestle, which carried four rail tracks, and replacing it with a fully functional precast concrete bridge. Each phase included the installation of an average of 22 girders.
“This project is our biggest one to date,” says Soncin. “It has been great to see the coordinated effort and there definitely is some pride in working on a project like this.”
Completion date for the project is slated for July 2008.
| MOST POPULAR STORIES |
- Korky Koroluk: Melting permafrost gives Canadian North that sinking feeling
- Two workers injured in separate accidents on Ontario’s Skyway Bridge
- Alberta continues to drive Canadian economy
- Volvo Construction Equipment cuts 500 jobs in Goderich
- Anthony Henday Drive ring road garners Canadian Design-Build Institute award
- 20 Most Popular Stories
| CURRENT STORIES |
- PCL Constructors team expands Air Canada Centre
- Debate sidesteps industry issues
- Ontario Realty Corporation registers general contractors, design firms online
- Stantec joins Infusion Health consortium on P3 hospital project
- Commercial banks stand to profit from Black Monday, economist says
- Economist warns U.S. economy on ‘slippery slope of recession’
- Daniels Corp. brings a taste of Chicago to Toronto condo project
- Facility and service managers must be full partners on P3 projects, expert says
- DCN election poll puts Stephen Harper’s Conservatives out in front
- Onni Group makes progress on Carlyle at Victoria Hill project
- Chinook Pipelines returns to court later this month in Pincher Creek case
| ALEX’S BLOG |

Reed Construction Data Chief Economist Alex Carrick discusses current developments in Canada's economic environment. He also shares light-hearted reflections on life and current events.
Economics Blog More 
- Huge Potential for Commercial Banks from Black Monday (October 3, 2008)
- Black Monday was Nasty for the U.S. and Canada (October 2, 2008)
- A 13-Step Action Plan to Fix the Financial Mess (September 30, 2008)
Lifestyle Blog More 
- Three Cities with a Lot in Common: Calgary, Edmonton and Venice (September 29, 2008)
- How to Get Ahead in this Life (September 25, 2008)
| PROJECT NEWS BRIEFS |
Updates on Canadian construction projects from Reed Construction Data’s research team. More 
- Viljoen Architects readies working drawings for Stonebridge by the Bay (Sep 15, 2008)
- REC Silicon plans $1.2-billion manufacturing plant in Quebec (Sep 15, 2008)
- Construction underway at Interfor’s Adams Lake sawmill (Sep 11, 2008)
- Alcan moves closer to construction of Kitimat aluminum smelter (Sep 11, 2008)
- Town of Oliver presses on with plans for wine village (Sep 11, 2008)
